Intersteel solar power plant - Serbia

Project statistics
40

kWp

installed capacity

CO2 emissions reduced by

23

tons

annually

Overview

Intersteel d.o.o. is one of the leaders in the area of ferrous metallurgy in the Republic of Serbia. After preliminary assessments made by Resalta, the Client opted for the construction of 40 kWp on the roof of its production facilities in Stara Pazova.

Resalta Solutions

In August 2022, Resalta completed all construction works, while the commissioning of the solar power plant took part in September. The solar power plant will produce 47 MWh of electricity and lead to a decrease in CO2 emissions by 23 tons per annum. The client is expected to be registered as a prosumer until the end of the year.

Chcete vidět víc?

Stáhněte si naši brožuru.

Pravidla a podmínky.

Přihlášením se k odběru našeho zpravodaje souhlasíte s přijímáním e-mailové komunikace od společnosti Resalta Czech republic s.r.o. Cílem našeho informačního bulletinu je informovat návštěvníky webových stránek, partnery, klienty a širokou veřejnost o práci, kterou společnost Resalta dělá, o jejích nových projektech, vývoji, nadcházejících událostech a novinkách týkajících se energetické účinnosti a obnovitelných zdrojů. Frekvence vydání zpravodaje bude nejvýše měsíčně, s možnými výjimkami pro neplánované, ale důležité zprávy. Vyhrazujeme si výhradní právo tento zpravodaj kdykoli změnit a ukončit, a to bez předchozího upozornění. Vaše soukromí bereme vážně a nikdy nebudeme vaše informace sdělovat ani prodávat třetím stranám. Odběr zpravodaje můžete kdykoli zrušit.